St. Johns Municipal Depot Renovation
St. John's, Newfoundland and Labrador
Federal contribution
$2.5M
$2,546,667
Federal share33%
of $7.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of St. John's
- Construction start
- Jul 1, 2009(actual)
- Construction end
- Aug 12, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2009
- Construction end3 months earlyforecast Oct 31, 2011
Also in St. John's