Back to projects

Route 15 - Scoudouc Industrial Park Interchange

Scoudouc, New Brunswick

completeHighways and RoadsISF
Federal contribution
$3.1M
$3,136,500
Federal share50%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
Nov 10, 2009(actual)
Construction end
Nov 19, 2010(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Nov 30, 2009
  • Construction end7 weeks lateforecast Sep 30, 2010

Also in Scoudouc

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34940 in the federal list. How to read these figures.