Scoudouc Industrial Park - Water Treatment Plant Upgrades
Federal contribution
$1.1M
$1,060,551
Federal share42%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.7 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Jul 11, 2022(actual)
- Construction end
- Sep 26, 2023(actual)
Against the original forecast
- Construction end6 months lateforecast Mar 25, 2023
Also in Scoudouc