Route 15 - Botsford Road to Painsec Junction
Federal contribution
$1.3M
$1,279,500
Federal share50%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built
Approved 14 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- Aug 19, 2009(actual)
- Construction end
- Nov 14, 2009(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 31, 2009
Also in Moncton
- Moncton Infrastructure Upgrades - Ashford Development$14.6M
- Moncton - Lutz, Robinson and Westmorland Street Reconstruction$10.8M
- Tower Road Dam and Reservoir (aka Turtle Creek)$9.8M
- City of Moncton - Blue Green Algae Abatement in Potable Water System (Phase 2)$8.8M
- Storm Sewer Renewal and Improvement$8.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34941 in the federal list. How to read these figures.