Minburn Road Grading
Federal contribution
$980,000
Federal share33%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipal District of Wainwright
- Construction start
- Jun 22, 2009(actual)
- Construction end
- Oct 31, 2010(actual)
Also in Wainwright
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35045 in the federal list. How to read these figures.