Back to projects

Town of Wainwright Sewer Upgrade

Wainwright, Alberta

completeWastewaterSCF
Federal contribution
$500,000
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
2016201820202022
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Wainwright
Construction start
Jul 26, 2020(actual)
Construction end
Nov 25, 2021(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Sep 1, 2020
  • Construction end4 months earlyforecast Mar 30, 2022