Blowers Street Sewer Rehabilitation

North Sydney, Nova Scotia

completeWastewaterISF
Federal contribution
$89,172
Federal share32%

of $278.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
May 12, 2010(actual)
Construction end
Sep 10, 2010(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast May 31, 2010
  • Construction end7 months earlyforecast Mar 31, 2011