King Street

North Sydney, Nova Scotia

completeWastewaterISF
Federal contribution
$179,999
Federal share33%

of $540.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
Sep 28, 2009(actual)
Construction end
Dec 10, 2010(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Dec 31, 2010