Upgrades to the Hope Arena
Fraser Valley, British Columbia
Federal contribution
$187,500
Federal share6%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional District of Fraser Valley
- Construction start
- Apr 20, 2009(actual)
- Construction end
- Aug 1, 2009(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 1, 2009
Also in Fraser Valley
- Fraser Valley - Cultus Lake North Wastewater Treatment Plant$5.5M
- Fraser Valley - Station House, Community Rest Stop and Museum: Boston Bar/North Bend, British Columbia$1.1M
- Fraser Valley - Hope and Area Recreation Centre Geothermal Heat Recovery$1.1M
- Electoral Area E - Baker Trails Estate Wastewater Treatment System Replacement$823.2K
- Boston Bar and Surrounding Area Fibre to the Home$254.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35255 in the federal list. How to read these figures.