Electoral Area E - Baker Trails Estate Wastewater Treatment System Replacement

Fraser Valley, British Columbia

completeWastewaterCWWF
Federal contribution
$823,175
Federal share50%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Dec 6, 2017(actual)
Construction end
Mar 15, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Sep 15, 2017
  • Construction end2 weeks lateforecast Mar 1, 2018

Also in Fraser Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47678 in the federal list. How to read these figures.