Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Apr 30, 2010(actual)
Construction end
Feb 28, 2011(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jul 31, 2010