New Habitat for Humanity facility
Federal contribution
$366,667
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Habitat for Humanity-Prince Edward-Hastings
- Construction start
- Apr 30, 2010(actual)
- Construction end
- Feb 28, 2011(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 31, 2010
Also in Belleville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35260 in the federal list. How to read these figures.