Replacement of the Outer Cove Bridge

Logy Bay-Middle Cove-Outer Cove, Newfoundland and Labrador

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,050,000
Federal share50%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJan 29, 2010
ApprovedMar 28, 2011
2011
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Mar 19, 2010(actual)
Construction end
Nov 26, 2010(actual)

Against the original forecast

  • Construction start6 months lateforecast Sep 15, 2009
  • Construction end4 weeks lateforecast Oct 31, 2010

Also in Logy Bay-Middle Cove-Outer Cove