2018 MCW Culvert Replacements

Logy Bay-Middle Cove-Outer Cove, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$65,601
Federal share22%

of $300.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 23, 2018(actual)
Construction end
Dec 4, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2018
  • Construction end2.8 years earlyforecast Sep 13, 2021

Also in Logy Bay-Middle Cove-Outer Cove

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51571 in the federal list. How to read these figures.