Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Ladysmith
- Construction start
- Jan 15, 2010(actual)
- Construction end
- Jun 15, 2011(actual)
Against the original forecast
- Construction start6 months earlyforecast Jul 5, 2010
- Construction end2 months lateforecast Mar 31, 2011