Back to projects

Ball Field

Ladysmith, British Columbia

completeSportISF
Federal contribution
$177,208
Federal share20%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Ladysmith
Construction start
Jan 15, 2010(actual)
Construction end
Jun 15, 2011(actual)

Against the original forecast

  • Construction start6 months earlyforecast Jul 5, 2010
  • Construction end2 months lateforecast Mar 31, 2011

Also in Ladysmith

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35303 in the federal list. How to read these figures.