Heart of the Hub - Phase 2
Federal contribution
$1.8M
$1,837,500
Federal share50%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2020202220242026
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Ladysmith
- Construction start
- Sep 5, 2024(actual)
- Construction end
- Mar 31, 2026(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Oct 31, 2024
- Construction end8 weeks lateforecast Jan 31, 2026
Also in Ladysmith
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56347 in the federal list. How to read these figures.