Memorial Hall Renovations

Harrison Hot Springs, British Columbia

completeRecreationISF
Federal contribution
$200,000
Federal share29%

of $700.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 18, 2010(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 1, 2010
  • Construction end3 months earlyforecast Mar 31, 2011

Also in Harrison Hot Springs

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35347 in the federal list. How to read these figures.