Schedule
Announced and approvedMay 2, 2014
20152016
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Harrison Hot Springs
- Construction start
- Oct 15, 2015(actual)
- Construction end
- Mar 31, 2016(actual)
Against the original forecast
- Construction start2 months earlyforecast Dec 15, 2015
Also in Harrison Hot Springs
- Harrison Hot Springs (HHS) Water Distribution$1.4M
- Hot Springs Road (Hwy 9) - Storm Sewer Infrastructure$800.0K
- Harrison Hot Springs - Fire Hall Renovation$593.0K
- Education and Child Care - School District 78 - Harrison Hot Springs Elementary Ventilation Improvements$248.0K
- Memorial Hall Renovations$200.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44858 in the federal list. How to read these figures.