Back to projects

Park Development

Coldstream, British Columbia

completeRecreationISF
Federal contribution
$187,500
Federal share30%

of $617.2K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Coldstream
Construction start
Sep 10, 2009(actual)
Construction end
Jul 30, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 1, 2009
  • Construction end3 months lateforecast May 2, 2010

Also in Coldstream

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35351 in the federal list. How to read these figures.