Coldstream Sewer Line Extension

Coldstream, British Columbia

completeWastewaterCWWF
Federal contribution
$50,856
Federal share50%

of $102.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
District of Coldstream
Construction start
Nov 17, 2017(actual)
Construction end
Jan 5, 2019(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 1, 2017
  • Construction end14 months lateforecast Nov 1, 2017

Also in Coldstream

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49873 in the federal list. How to read these figures.