Storm Sewer, Street and Sidewalk Renewal
Federal contribution
$200,000
Federal share27%
of $730.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Hazelton
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Aug 25, 2010(actual)
Also in Hazelton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35452 in the federal list. How to read these figures.