Hazelton - River Road Active Transportation Upgrades and Road Works

Hazelton, British Columbia

completeActive TransportationRNIS
Federal contribution
$784,724
Federal share40%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
20232024
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Hazelton
Construction start
Jun 13, 2023(actual)
Construction end
Jul 9, 2024(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2023
  • Construction end5 months earlyforecast Dec 1, 2024

Also in Hazelton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61571 in the federal list. How to read these figures.