Qualicum Beach Roundabout

Qualicum Beach, British Columbia

completeHighways and RoadsISF
Federal contribution
$187,500
Federal share29%

of $637.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Qualicum Beach
Construction start
Aug 10, 2009(actual)
Construction end
Oct 1, 2009(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2009
  • Construction end18 months earlyforecast Mar 31, 2011

Also in Qualicum Beach

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35472 in the federal list. How to read these figures.