Fred Victor Community Services Centre Renovation
Federal contribution
$1.1M
$1,100,599
Federal share33%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Fred Victor Centre
- Construction start
- Jan 4, 2010(actual)
- Construction end
- Aug 31, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Oct 19, 2009
- Construction end3 months lateforecast May 31, 2011
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35477 in the federal list. How to read these figures.