Water System Improvements

Thompson-Nicola, British Columbia

completeDrinking WaterISF
Federal contribution
$181,462
Federal share33%

of $544.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Feb 20, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jan 31, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Thompson-Nicola

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35497 in the federal list. How to read these figures.