Highway 104 Repaving
Federal contribution
$1.7M
$1,740,263
Federal share44%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
Built
Approved 4 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Sep 16, 2009(actual)
- Construction end
- Nov 24, 2009(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 26, 2009
- Construction end3 weeks lateforecast Oct 31, 2009
Also in Antigonish
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35499 in the federal list. How to read these figures.