North East Light Rail Transit Signal System Upgrade

Edmonton, Alberta

completePublic TransitISF
Federal contribution
$9.9M
$9,933,333
Federal share33%

of $29.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 19, 2009
ApprovedSep 8, 2009
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Edmonton
Construction start
Aug 9, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2010
  • Construction end3 months lateforecast Jul 31, 2011