North East Light Rail Transit Signal System Upgrade
Federal contribution
$9.9M
$9,933,333
Federal share33%
of $29.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 19, 2009
ApprovedSep 8, 2009
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Edmonton
- Construction start
- Aug 9, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2010
- Construction end3 months lateforecast Jul 31, 2011
Also in Edmonton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35508 in the federal list. How to read these figures.