Back to projects

Road Reconstruction

Salmo, British Columbia

completeHighways and RoadsISF
Federal contribution
$150,475
Federal share33%

of $451.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Salmo
Construction start
Jul 21, 2009(actual)
Construction end
Sep 16, 2009(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 1, 2009
  • Construction end18 months earlyforecast Mar 31, 2011

Also in Salmo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35515 in the federal list. How to read these figures.