Sewage System Upgrade and Improvements

Salmo, British Columbia

completeWastewaterCWWF
Federal contribution
$1.0M
$1,046,250
Federal share50%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018201920202021
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Salmo
Construction start
Aug 1, 2017(actual)
Construction end
Feb 26, 2021(actual)

Against the original forecast

  • Construction start15 months earlyforecast Oct 29, 2018
  • Construction end2 weeks earlyforecast Mar 13, 2021

Also in Salmo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49762 in the federal list. How to read these figures.