Arena Upgrade - Invermere
Federal contribution
$187,500
Federal share22%
of $854.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional District of East Kootenay
- Construction start
- Apr 5, 2010(actual)
- Construction end
- Aug 31, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Mar 1, 2010
Also in Invermere
- Nzen'man' Bird's Nest$8.5M
- Paddy Ryan Water Treatment Plant UV Disinfection Upgrade$908.5K
- Invermere - Toby Creek Dike Improvements$883.6K
- Invermere - Climate Change Mitigation and Flooding/Stormwater Management Improvements$629.4K
- Columbia Valley Greenways Trail Alliance - Markin-MacPhail Westside Legacy Trail$540.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35516 in the federal list. How to read these figures.