Paddy Ryan Water Treatment Plant UV Disinfection Upgrade

Invermere, British Columbia

completeDrinking WaterCWWF
Federal contribution
$908,481
Federal share50%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Community of Invermere
Construction start
May 15, 2017(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction end2 months lateforecast Aug 31, 2018