Edmonton Transit - South Light Rail Transit Platform Extension to 5-Car Length
Federal contribution
$2.8M
$2,819,924
Federal share19%
of $15.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 19, 2009
ApprovedSep 8, 2009
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Edmonton
- Construction start
- Jul 9, 2009(actual)
- Construction end
- Apr 24, 2011(actual)
Against the original forecast
- Construction start6 months earlyforecast Jan 2, 2010
- Construction end3 weeks lateforecast Mar 31, 2011