Frank Street Well Emergency Generator
Federal contribution
$149,143
Federal share33%
of $447.4K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Terrace
- Construction start
- Jul 5, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Sep 1, 2009
- Construction end2 months lateforecast Sep 1, 2011
Also in Terrace
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35550 in the federal list. How to read these figures.