Headwaters Walkway
Federal contribution
$101,333
Federal share33%
of $304.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Canal Flats
- Construction start
- Aug 12, 2009(actual)
- Construction end
- Sep 30, 2009(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Oct 31, 2009
Also in Canal Flats