Canal Flats - Dike Upgrade Design and Construction

Canal Flats, British Columbia

completeDisaster MitigationCVRIS
Federal contribution
$873,600
Federal share80%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 5, 2022
20222023202420252026
Built

Approved 16 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Village of Canal Flats
Construction start
May 1, 2023(actual)
Construction end
Nov 30, 2025(actual)

Against the original forecast

  • Construction start9 months lateforecast Jul 31, 2022

Also in Canal Flats

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59827 in the federal list. How to read these figures.