Well Water No. 1 - Backup Power

Houston, British Columbia

completeDrinking WaterISF
Federal contribution
$80,043
Federal share33%

of $240.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Houston
Construction start
Jan 11, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Feb 17, 2010