Maison Saint-Gabriel Expansion
Federal contribution
$2.0M
$1,988,492
Federal share31%
of $6.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 10, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Maison Saint-Gabriel Museum
- Construction start
- Dec 30, 2009(actual)
- Construction end
- Jan 6, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Dec 15, 2009
- Construction end6 weeks lateforecast Nov 22, 2010