Program for the renewal of drinking water and wastewater pipes
Notre-Dame-des-Prairies, Quebec
Federal contribution
$653,016
Federal share31%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 8, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Notre-Dame-des-Prairies
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
Also in Notre-Dame-des-Prairies
- Construction of an indoor refrigerated ice rink$1.5M
- Development of the active transportation network - Linking the residential area to the school, recreational, cultural and community perimeter of 3e avenue and Gauthier Nord street in Notre-Dame-des-Pr$835.4K
- Drinking Water Network Extension on Rang Sainte-Julie$290.5K
- Program for the renewal of drinking water and wastewater pipes$241.5K
- Program for the renewal of drinking water and wastewater pipes$194.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35712 in the federal list. How to read these figures.