Federal contribution
$290,547
Federal share40%

of $726.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 17, 2020
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Aug 31, 2020(actual)
Construction end
Nov 11, 2020(actual)