Renewal and extension of municipal infrastructure under Robitaille Street
Federal contribution
$1.4M
$1,408,617
Federal share31%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 27, 2009
20102011201220132014
Built
Approved 2 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Granby
- Construction start
- Dec 4, 2009(actual)
- Construction end
- Jan 31, 2014(actual)
Against the original forecast
- Construction start5 months earlyforecast May 20, 2010
- Construction end3.4 years lateforecast Aug 20, 2010
Also in Granby