Back to projects

Water Systems Upgrades

Granby, Quebec

completeWastewaterGIS
Federal contribution
$2.0M
$1,996,984
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Granby
Construction start
May 10, 2021(actual)
Construction end
Oct 18, 2021(actual)

Also in Granby