Repairs to Highway 55 in Sherbrooke
Federal contribution
$1.1M
$1,092,941
Federal share46%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- May 28, 2010(actual)
- Construction end
- Sep 17, 2010(actual)
Against the original forecast
- Construction start2 months earlyforecast Aug 1, 2010
Also in Sherbrooke
- South bypass of the Sherbrooke agglomeration by extending Highway 410 - Phase II$35.6M
- Expansion of Cabana Operations Center$30.8M
- Acquisition of 40 electric buses$24.8M
- Multipurpose Centre at Bishop's University - Sherbrooke$13.2M
- Renovation of Sherbrooke, Deauville and Brompton water treatment plants$6.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35780 in the federal list. How to read these figures.