Trail Upgrades at Lundbreck Falls Provincial Recreation Area
Federal contribution
$24,944
Federal share50%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- May 18, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jul 1, 2010
- Construction end3 months lateforecast Jan 1, 2011
Also in Edmonton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35816 in the federal list. How to read these figures.