Playground at Touchwood Lake

Lac La Biche County, Alberta

completeRecreationISF
Federal contribution
$18,605
Federal share47%

of $40.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Aug 1, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2010

Also in Lac La Biche County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35867 in the federal list. How to read these figures.