Campsite Upgrades at Smoke Iosegun Provincial Park

Edmonton, Alberta

completeRecreationISF
Federal contribution
$37,500
Federal share50%

of $75.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 1, 2010(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jul 1, 2010