Québec and Sainte-Foy Water System Interconnection
Federal contribution
$13.2M
$13,165,631
Federal share24%
of $55.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Québec
- Construction start
- Mar 15, 2010(actual)
- Construction end
- Jul 14, 2011(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Apr 12, 2010
- Construction end2 weeks lateforecast Jun 30, 2011
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35913 in the federal list. How to read these figures.