Multigenerational Training Centre
Federal contribution
$3.2M
$3,162,341
Federal share32%
of $9.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of L'Ancienne-Lorette
- Construction start
- Apr 20, 2010(actual)
- Construction end
- Jul 22, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Mar 15, 2010