Water Systems Upgrade
Federal contribution
$2.0M
$1,983,344
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2020
2021
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of L'Ancienne-Lorette
- Construction start
- May 1, 2020(actual)
- Construction end
- Dec 31, 2020(actual)
Against the original forecast
- Construction start4 months earlyforecast Aug 24, 2020
- Construction end8 months earlyforecast Aug 31, 2021
Also in L'Ancienne-Lorette
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56327 in the federal list. How to read these figures.