Bridge Replacement in Glen Bain
Glen Bain No. 105, Saskatchewan
Federal contribution
$175,000
Federal share33%
of $525.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Feb 1, 2010(actual)
- Construction end
- Jun 4, 2010(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Feb 22, 2010
- Construction end8 weeks earlyforecast Aug 1, 2010
Also in Glen Bain No. 105
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35938 in the federal list. How to read these figures.