RM of Glen Bain No. 105, Kornaga Bridge Rehabilitation

Glen Bain No. 105, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$166,700
Federal share17%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2022
2023
Built

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
RM of Glen Bain No. 105
Construction start
Jan 9, 2023(actual)
Construction end
Mar 29, 2023(actual)

Against the original forecast

  • Construction end14 months earlyforecast May 31, 2024

Also in Glen Bain No. 105

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61379 in the federal list. How to read these figures.