Bridge Replacement in Gravelbourg

Gravelbourg, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$150,000
Federal share33%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Saskatchewan
Construction start
Feb 1, 2010(actual)
Construction end
Jun 4, 2010(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Feb 22, 2010
  • Construction end3 months earlyforecast Aug 31, 2010

Also in Gravelbourg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35939 in the federal list. How to read these figures.