Bridge Replacement in Gravelbourg
Federal contribution
$150,000
Federal share33%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Feb 1, 2010(actual)
- Construction end
- Jun 4, 2010(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Feb 22, 2010
- Construction end3 months earlyforecast Aug 31, 2010
Also in Gravelbourg
- Town of Gravelbourg Water Tower Decommissioning and Watermain Replacement$1.4M
- Gravelbourg Water Treatment Plant Upgrades - Phase 2$1.0M
- Town of Gravelbourg-Landfill Decommissioning$495.3K
- Town of Gravelbourg-Water Treatment Plant Upgrade$250.0K
- Purchase of a hybrid vehicle and construction of a garage for on-demand service in Gravelbourg and rural southwest Saskatchewan$78.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35939 in the federal list. How to read these figures.